Morocco Workshop

--Only two anchor bolts per column in the workshop with 5T crane

Morocco Workshop
Morocco Workshop
Morocco Workshop
Morocco Workshop
Morocco Workshop
Morocco Workshop
Morocco Workshop
Morocco Workshop
  • Country:

    Morocco

  • Year:

    2020

After multiple discussions, this client still chose the hinged base connection method to save on construction costs, using only two sets anchor bolts per column.


Morocco workshop
--Only two anchor bolts per column in the workshop with 5T crane
CountryMoroccoYear2020
Project Information
ProjectSteel Structure workshopDimension70*24*7m(with sky window)Wind speed29m/s
MaterialH-steelPaintAlykd paintPurlineC purline
160x60x20x2
RoofEPS sandwich panel (0.47mm+50mm 12kg+0.37mm)+1mm sky light sheetWall PPGI
single corrugated sheet
V900 0.5mm
WindowAlluminum alloy
sliding window, 1mm frame+0.5mm tempered glass 3mx1.5mx24
DoorSandwich panel
sliding door 5mx6mx2
  Containers6x40HQ

 

In our engineer's knowledge, this design is unreasonable and unsafe for steel structure buildings, so we communicated with this client many times to ensure their design was good. This client's architect is also very professional and likely integrated local standards, so we ultimately manufactured according to this client's design requirements.


Steel Structure workshop

 

This steel structure workshop is also equipped with a 5-ton crane, which was provided by us. We have reliable cooperated supplier and the price is competitive.


Steel Structure workshop

 

After several design changes and communications, this client confirmed the order with a payment term 30% deposit by TT and 70% balance by LC.


Steel Structure workshop

 

Due to the pandemic, shipping costs skyrocketed, rising from over $3,000 to $20,000 of a 40HQ container. This project needed 7x40HQ containers, as facing the high shipping fees, client postponed the shipment. It wasn't until a year and a half later, when the shipping costs dropped to $8,000, that the shipment was sent.


Steel Structure workshop

 

During this period, we waived the storage fees for this client`s steel structure workshop. We sincerely apologize for this unusual situation and have done our best to minimize this client's losses within our capabilities.